Project overview

Organisation: NHS Greater Glasgow & Clyde
Hospital: NHS Stobhill Hospital
Project: Rapid Assessment Unit Refurbishment
Value: £150, 000
Timescale: 2007

Project specifics:

  • 9 week project
  • Adapting an open space visual approach
  • Introducing cosmetic standard
  • Replacing copper pipework with stainless steel
  • Upgrading electricity
  • Removal of Asbestos

Rapid Assessment Unit - Stobhill

This was a simple refurbishment project concentrating on more open space visual approach. Cosmetic standard was introduced for future consideration within NHS facilities. Enhanced reception area was introduced for betterment to all concerned.

Usual issues were present such as upgrading infrastructure as existing was decaying and in some cases defective. Most of the hospitals old domestic water pipe work was copper, which through time corrodes. New stainless steel pipe work was introduced as standard. New Electrical upgrade included the upgrade of Electrical boards.

Asbestos removal was one of the key factors to allow main works to commence.

Works carried out over 9 weeks

Total value of project was £150,000.00